Dept. of Trans. PROGRESS Serial No. Contract No. 20-252-08-52 06-0X1804 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 16% Location: Federal Project: 06-KER-0 NONE Progress payment No. 001 Payment period ending: 08-20-20 TPA CONSTRUCTION INC 2406 CLUBHOUSE DRIVE ROCKLIN CA 95765 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 254,727.72 254,727.72 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 254,727.72 254,727.72 5. Mobilization 75,000.00 75,000.00 6. Total Work Completed 329,727.72 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 329,727.72 329,727.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 329,727.72