Dept. of Trans. PROGRESS Serial No. Contract No. 20-323-12-28 06-0X2004 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 100% Location: Federal Project: 06-KER-119-R9.8/R13.3 NONE Progress payment No. 009 Payment period ending: 11-20-20 BOSCO CONSTRUCTORS INC 21353 MAYALL ST CHATSWORTH CA 91311 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 770,125.68 9,715.20 2. a. Extra Work 38,005.34 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 808,131.02 9,715.20 5. Mobilization 6. Total Work Completed 808,131.02 7. Deductions -5,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 803,131.02 9,715.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,715.20