Dept. of Trans. PROGRESS Serial No. Contract No. 25-295-06-59 06-0X2404 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 54% Location: Federal Project: 06-KER-33-21.8/39.8 NONE Progress payment No. 004 Payment period ending: 10-20-25 DOJA INC 5050 MISSION BLVD ONTARIO CA 91762 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 609,456.90 167,832.70 2. a. Extra Work 34,297.05 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 643,753.95 167,832.70 5. Mobilization 240,000.83 0.00 6. Total Work Completed 883,754.78 7. Deductions -27,407.87 2,592.13 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 856,346.91 170,424.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 170,424.83