Dept. of Trans. PROGRESS Serial No. Contract No. 26-299-11-27 06-0X2404 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 89% Location: Federal Project: 06-KER-33-21.8/39.8 NONE Progress payment No. 010 Payment period ending: 10-20-26 DOJA INC 5050 MISSION BLVD ONTARIO CA 91762 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,294,602.60 -36,204.50 2. a. Extra Work 156,911.70 61,911.85 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,451,514.30 25,707.35 5. Mobilization 304,001.05 0.00 6. Total Work Completed 1,755,515.35 7. Deductions -255,232.20 -11,248.77 8. a. Contract Retentions b. Unsatisfactory Retentions -44,739.60 -2,570.74 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,455,543.55 11,887.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,887.84