Dept. of Trans. PROGRESS Serial No. Contract No. 25-143-11-00 06-0X2504 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 23% Location: Federal Project: 06-TUL-99-20.8/53.1 PTNH-P099(691) Progress payment No. 002 Payment period ending: 05-20-25 GRANITE CONSTRUCTION COMPANY 580 WEST BEACH ST WATSONVILLE CA 95076 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 511,776.00 144,046.08 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 511,776.00 144,046.08 5. Mobilization 199,500.00 42,000.00 6. Total Work Completed 711,276.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 711,276.00 186,046.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 186,046.08