Dept. of Trans. PROGRESS Serial No. Contract No. 24-292-17-14 06-0X2804 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 76% Location: Federal Project: 06-FRE-5-60.1/66.2 ACIM-005(5) Progress payment No. 005 Payment period ending: 10-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,547,004.54 1,513,296.40 2. a. Extra Work b. Adustment Comp. -8,175.00 0.00 3. Materials on Hand 178,350.00 0.00 4. Earned Subject to Retention 10,717,179.54 1,513,296.40 5. Mobilization 1,300,000.00 0.00 6. Total Work Completed 11,838,829.54 7. Deductions -55,000.00 -55,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,962,179.54 1,458,296.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,458,296.40