Dept. of Trans. PROGRESS Serial No. Contract No. 25-021-13-05 06-0X3804 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 98% Location: Federal Project: 06-KER-166-0.0/10.2 ACST-S166(3) Progress payment No. 009 Payment period ending: 01-20-25 GRIFFITH COMPANY 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,117,205.36 407,294.89 2. a. Extra Work 56,903.39 39,181.54 b. Adustment Comp. 83,155.00 83,155.00 3. Materials on Hand 60,207.01 6,955.01 4. Earned Subject to Retention 10,317,470.76 536,586.44 5. Mobilization 1,000,000.00 0.00 6. Total Work Completed 11,257,263.75 7. Deductions -470,815.15 -72,500.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,846,655.61 464,086.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 464,086.44