Dept. of Trans. PROGRESS Serial No. Contract No. 25-237-13-24 06-0X3804 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 100% Location: Federal Project: 06-KER-166-0.0/10.2 ACST-S166(3) Progress payment No. 015 Payment period ending: 08-20-25 GRIFFITH COMPANY 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,063,361.16 151,146.65 2. a. Extra Work 391,329.16 255,009.14 b. Adustment Comp. 83,155.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 11,537,845.32 406,155.79 5. Mobilization 1,000,000.00 0.00 6. Total Work Completed 12,537,845.32 7. Deductions -168,318.66 -21,029.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,369,526.66 385,126.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 385,126.79