Dept. of Trans. FINAL Serial No. Contract No. 19-073-09-04 06-0X4604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-KER-5-0.0/87.0 NONE Progress payment No. 008 Payment period ending: 09-24-18 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,084,849.32 0.00 2. a. Extra Work 273,732.57 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 3,358,581.89 0.00 5. Mobilization 6. Total Work Completed 3,358,581.89 7. Deductions 0.00 20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,358,581.89 20,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 20,000.00