Dept. of Trans. PROGRESS Serial No. Contract No. 23-262-10-10 06-0X7604 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 91% Location: Federal Project: 06-KER-119-0.2/0.6 HSST-S119(21) Progress payment No. 006 Payment period ending: 09-20-23 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,183,594.15 982.00 2. a. Extra Work 5,269.80 0.00 b. Adustment Comp. -10,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,178,863.95 982.00 5. Mobilization 129,000.00 0.00 6. Total Work Completed 1,307,863.95 7. Deductions -6,800.62 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,301,063.33 982.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 982.00