Dept. of Trans. SEMI-FINAL Serial No. Contract No. 24-072-11-16 06-0X7604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-KER-119-0.2/0.6 HSST-S119(21) Progress payment No. 009 Payment period ending: 01-30-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,222,887.25 0.00 2. a. Extra Work 5,269.80 0.00 b. Adustment Comp. -15,311.01 7,441.13 3. Materials on Hand 4. Earned Subject to Retention 1,212,846.04 7,441.13 5. Mobilization 129,000.00 0.00 6. Total Work Completed 1,341,846.04 7. Deductions -42,101.90 6,800.62 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,299,744.14 14,241.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 14,241.75