Dept. of Trans. FINAL Serial No. Contract No. 24-291-14-00 06-0X7604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-KER-119-0.2/0.6 HSST-S119(21) Progress payment No. 011 Payment period ending: 01-30-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,225,642.25 0.00 2. a. Extra Work 64,639.04 0.00 b. Adustment Comp. -15,311.01 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,274,970.28 0.00 5. Mobilization 129,000.00 0.00 6. Total Work Completed 1,403,970.28 7. Deductions -39,511.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,364,459.28 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00