Dept. of Trans. PROGRESS Serial No. Contract No. 19-234-14-39 06-0X8304 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 91% Location: Federal Project: 06-KER-33-44.2/54.0 ACST-P033(91) Progress payment No. 002 Payment period ending: 08-20-19 GRIFFITH COMPANY 1128 CARRIER PKWY AV BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,894,252.03 568,483.41 2. a. Extra Work b. Adustment Comp. -25,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,869,252.03 568,483.41 5. Mobilization 6. Total Work Completed 1,869,252.03 7. Deductions -142,120.85 -142,120.85 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,727,131.18 426,362.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 426,362.56