Dept. of Trans. PROGRESS Serial No. Contract No. 19-143-14-32 06-0X8904 PROGRESS PAYMENT VOUCHER %complete: %time: 24% 13% Location: Federal Project: 06-KIN-41-0.0/11.5 NONE Progress payment No. 002 Payment period ending: 05-20-19 PAPICH CONSTRUCTION COMPANY INC 398 SUNRISE TERRACE ARROYO GRANDE CA 93420 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 116,059.56 -638,370.58 2. a. Extra Work 644,255.18 644,255.18 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 760,314.74 5,884.60 5. Mobilization 6. Total Work Completed 760,314.74 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 760,314.74 5,884.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,884.60