Dept. of Trans. PROGRESS Serial No. Contract No. 26-054-08-10 06-0Y1304 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 93% Location: Federal Project: 06-KER-33-40.4/59.3 ACST-S033(94) Progress payment No. 017 Payment period ending: 02-20-26 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,672,517.68 630,385.61 2. a. Extra Work 258,489.62 70,221.27 b. Adustment Comp. 258,630.54 -151,910.50 3. Materials on Hand 4. Earned Subject to Retention 25,189,637.84 548,696.38 5. Mobilization 2,400,000.00 0.00 6. Total Work Completed 27,589,637.84 7. Deductions -43,643.75 -30,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 27,545,994.09 518,696.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 518,696.38