Dept. of Trans. PROGRESS Serial No. Contract No. 22-356-14-28 06-0Y4904 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 41% Location: Federal Project: 06-FRE-0-0.0 SSTG-000C(537) Progress payment No. 006 Payment period ending: 12-20-22 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,000,334.09 196,450.69 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 1,293,004.00 -13,275.29 4. Earned Subject to Retention 2,293,338.09 183,175.40 5. Mobilization 200,450.00 0.00 6. Total Work Completed 1,200,784.09 7. Deductions -20,000.00 20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,473,788.09 203,175.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 203,175.40