Dept. of Trans. PROGRESS Serial No. Contract No. 23-053-13-02 06-0Y4904 PROGRESS PAYMENT VOUCHER %complete: %time: 29% 51% Location: Federal Project: 06-FRE-0-0.0 SSTG-000C(537) Progress payment No. 008 Payment period ending: 02-20-23 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,574,372.81 559,078.72 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 1,287,919.51 -77,308.65 4. Earned Subject to Retention 2,862,292.32 481,770.07 5. Mobilization 200,450.00 0.00 6. Total Work Completed 1,774,822.81 7. Deductions -20,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,042,742.32 491,770.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 491,770.07