Dept. of Trans. PROGRESS Serial No. Contract No. 23-080-18-07 06-0Y4904 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 48% Location: Federal Project: 06-FRE-0-0.0 SSTG-000C(537) Progress payment No. 009 Payment period ending: 03-20-23 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,880,901.70 306,528.89 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 1,217,909.16 -70,010.35 4. Earned Subject to Retention 3,098,810.86 236,518.54 5. Mobilization 211,000.00 10,550.00 6. Total Work Completed 2,091,901.70 7. Deductions -21,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,288,810.86 246,068.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 246,068.54