Dept. of Trans. PROGRESS Serial No. Contract No. 23-114-16-04 06-0Y4904 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 54% Location: Federal Project: 06-FRE-0-0.0 SSTG-000C(537) Progress payment No. 010 Payment period ending: 04-20-23 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,248,352.22 367,450.52 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 1,049,339.05 -168,570.11 4. Earned Subject to Retention 3,297,691.27 198,880.41 5. Mobilization 211,000.00 0.00 6. Total Work Completed 2,459,352.22 7. Deductions -22,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,486,691.27 197,880.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 197,880.41