Dept. of Trans. PROGRESS Serial No. Contract No. 23-139-15-18 06-0Y4904 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 60% Location: Federal Project: 06-FRE-0-0.0 SSTG-000C(537) Progress payment No. 011 Payment period ending: 05-20-23 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,679,451.26 431,099.04 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 843,588.37 -205,750.68 4. Earned Subject to Retention 3,523,039.63 225,348.36 5. Mobilization 211,000.00 0.00 6. Total Work Completed 2,890,451.26 7. Deductions -22,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,712,039.63 225,348.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 225,348.36