Dept. of Trans. PROGRESS Serial No. Contract No. 23-167-16-16 06-0Y4904 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 61% Location: Federal Project: 06-FRE-0-0.0 SSTG-000C(537) Progress payment No. 012 Payment period ending: 06-20-23 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,060,851.39 381,400.13 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 826,621.57 -16,966.80 4. Earned Subject to Retention 3,887,472.96 364,433.33 5. Mobilization 211,000.00 0.00 6. Total Work Completed 3,271,851.39 7. Deductions -20,000.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,078,472.96 366,433.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 366,433.33