Dept. of Trans. PROGRESS Serial No. Contract No. 23-207-11-23 06-0Y4904 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 76% Location: Federal Project: 06-FRE-0-0.0 SSTG-000C(537) Progress payment No. 013 Payment period ending: 07-20-23 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,461,869.96 401,018.57 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 727,983.15 -98,638.42 4. Earned Subject to Retention 4,189,853.11 302,380.15 5. Mobilization 211,000.00 0.00 6. Total Work Completed 3,672,869.96 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,380,853.11 302,380.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 302,380.15