Dept. of Trans. PROGRESS Serial No. Contract No. 23-262-10-31 06-0Y4904 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 84% Location: Federal Project: 06-FRE-0-0.0 SSTG-000C(537) Progress payment No. 015 Payment period ending: 09-20-23 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,226,476.57 327,256.97 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 447,134.33 -143,953.77 4. Earned Subject to Retention 4,673,610.90 183,303.20 5. Mobilization 211,000.00 0.00 6. Total Work Completed 4,437,476.57 7. Deductions -40,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,844,610.90 183,303.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 183,303.20