Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 24-040-10-27 06-0Y4904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-FRE-0-0.0 SSTG-000C(537) Progress payment No. 017 Payment period ending: 02-02-24 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,916,524.90 279,128.86 2. a. Extra Work 275,057.02 275,057.02 b. Adustment Comp. 3. Materials on Hand 0.00 -728,289.75 4. Earned Subject to Retention 5,191,581.92 -174,103.87 5. Mobilization 211,000.00 0.00 6. Total Work Completed 5,402,581.92 7. Deductions -270,058.00 -210,058.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,132,523.92 -384,161.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -384,161.87