Dept. of Trans. PROGRESS Serial No. Contract No. 22-298-13-25 06-0Y7904 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 93% Location: Federal Project: 06-FRE-180-R58.8/R58.8 HSST-P180(61) Progress payment No. 003 Payment period ending: 10-20-22 FBD VANGUARD CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 621,102.80 211,909.30 2. a. Extra Work b. Adustment Comp. 30.63 30.63 3. Materials on Hand 4. Earned Subject to Retention 621,133.43 211,939.93 5. Mobilization 6. Total Work Completed 621,133.43 7. Deductions -96,000.00 -90,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 525,133.43 121,939.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 121,939.93