Dept. of Trans. PROGRESS Serial No. Contract No. 20-236-14-57 06-1A2304 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 69% Location: Federal Project: 06-KER-33-40.0/44.2 NONE 06-KIN-33-7.8/12.0 Progress payment No. 004 Payment period ending: 08-20-20 PAPICH CONSTRUCTION COMPANY INC 398 SUNRISE TERRACE ARROYO GRANDE CA 93420 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,805,895.51 97,365.70 2. a. Extra Work 5,523.50 5,523.50 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,811,419.01 102,889.20 5. Mobilization 6. Total Work Completed 2,811,419.01 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,801,419.01 92,889.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 92,889.20