Dept. of Trans. PROGRESS Serial No. Contract No. 24-201-13-07 06-1A7504 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 77% Location: Federal Project: 06-FRE-5-26.8/30.0 SIMG-005(5) Progress payment No. 003 Payment period ending: 07-20-24 CALIFORNIA HIGHWAY CONSTRUCTION GROUP INC 1647 WILLOW PASS RD #150 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,459,822.35 199,210.55 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -103,474.00 4. Earned Subject to Retention 1,459,822.35 95,736.55 5. Mobilization 123,570.00 0.00 6. Total Work Completed 1,583,392.35 7. Deductions -40,000.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,543,392.35 75,736.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 75,736.55