Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 21-292-15-28 06-1A9304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-KER-5-56.6/58.1 NONE 06-KER-5-77.0/80.0 Progress payment No. 002 Payment period ending: 09-28-21 BIG DOG EQUIPMENT SERVICES INC 16555 SIERRA HWY CANYON COUNTRY CA 91351 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 803,192.00 477,112.50 2. a. Extra Work 40,000.00 40,000.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 843,192.00 517,112.50 5. Mobilization 6. Total Work Completed 843,192.00 7. Deductions -266,330.47 -266,330.47 8. a. Contract Retentions b. Unsatisfactory Retentions 0.00 32,607.95 c. Reduction after 95% Comp. 9. Total pay to Contractor 576,861.53 283,389.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 283,389.98