Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 21-362-10-37 06-1A9504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-KER-46-51.2/57.8 NONE 06-KER-65-0.7/6.9 Progress payment No. 006 Payment period ending: 11-18-21 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,066,897.01 -360.00 2. a. Extra Work b. Adustment Comp. 63,290.11 32,605.02 3. Materials on Hand 4. Earned Subject to Retention 3,130,187.12 32,245.02 5. Mobilization 6. Total Work Completed 3,130,187.12 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,110,187.12 32,245.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 32,245.02