Dept. of Trans. PROGRESS Serial No. Contract No. 23-023-12-54 06-1C4304 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 97% Location: Federal Project: 06-MAD-41-9.2/11.7 NONE 06-MAD-99-0.0/1.5 Progress payment No. 006 Payment period ending: 01-20-23 CAL VALLEY CONSTRUCTION INC 5125 N. GATES AVE #102 FRESNO CA 93722 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,456,027.38 188,642.70 2. a. Extra Work b. Adustment Comp. 22,078.89 1,847.16 3. Materials on Hand 4. Earned Subject to Retention 2,478,106.27 190,489.86 5. Mobilization 6. Total Work Completed 2,478,106.27 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,468,106.27 180,489.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 180,489.86