Dept. of Trans. PROGRESS Serial No. Contract No. 22-026-13-22 06-1C6504 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 100% Location: Federal Project: 06-FRE-41-0.5/5.7 NONE Progress payment No. 005 Payment period ending: 01-20-22 CAL VALLEY CONSTRUCTION INC 5125 N. GATES AVE #102 FRESNO CA 93722 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,764,698.66 23,981.53 2. a. Extra Work 83,513.32 83,513.32 b. Adustment Comp. 608,950.83 -880.16 3. Materials on Hand 4. Earned Subject to Retention 5,457,162.81 106,614.69 5. Mobilization 675,000.00 0.00 6. Total Work Completed 6,132,162.81 7. Deductions -131,818.10 -66,700.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,000,344.71 39,914.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 39,914.69