Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 23-082-13-11 06-1E0504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-KER-65 NONE 06-KER-223 Progress payment No. 004 Payment period ending: 11-16-22 CENTRAL COAST FINANCIAL GROUP INC 17750 WARDS FERRY RD SONORA CA 95370 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 857,619.74 1,800.00 2. a. Extra Work 4,029.08 4,029.08 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 861,648.82 5,829.08 5. Mobilization 6. Total Work Completed 861,648.82 7. Deductions -30,000.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 831,648.82 -14,170.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -14,170.92