Dept. of Trans. FINAL Serial No. Contract No. 24-072-15-30 06-1E5704 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-FRE-145-26.1/34.1 NONE 06-MAD-145-2.0/8.0 Progress payment No. 005 Payment period ending: 09-29-23 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,512,205.40 286.00 2. a. Extra Work 31,298.78 0.00 b. Adustment Comp. 5,567.09 -7,341.33 3. Materials on Hand 4. Earned Subject to Retention 4,549,071.27 -7,055.33 5. Mobilization 6. Total Work Completed 4,549,071.27 7. Deductions 0.00 20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,549,071.27 12,944.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 12,944.67