Dept. of Trans. PROGRESS Serial No. Contract No. 23-205-09-52 06-1E6904 PROGRESS PAYMENT VOUCHER %complete: %time: 69% 9% Location: Federal Project: 06-TUL-99-9.8/40.7 NONE Progress payment No. 004 Payment period ending: 07-20-23 MARINA LANDSCAPE INC. 3707 W GARDEN GROVE BLVD ORANGE CA 92868 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 291,818.00 69,711.50 2. a. Extra Work 40,281.66 35,219.45 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 332,099.66 104,930.95 5. Mobilization 38,000.00 0.00 6. Total Work Completed 370,099.66 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 370,099.66 104,930.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 104,930.95