Dept. of Trans. PROGRESS Serial No. Contract No. 25-055-09-39 06-1E7704 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 94% Location: Federal Project: 06-KER-204-2.1/4.6 NONE Progress payment No. 007 Payment period ending: 02-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,751,919.35 460,125.20 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 3,751,919.35 460,125.20 5. Mobilization 350,000.00 0.00 6. Total Work Completed 4,101,919.35 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,081,919.35 460,125.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 460,125.20