Dept. of Trans. SEMI-FINAL Serial No. Contract No. 24-127-13-05 06-1F2504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-KER-43-15.9/37.8 NONE Progress payment No. 007 Payment period ending: 01-25-24 LAMASSU UTILITY SERVICES INC 3193 ENTERPRISE CT LOOMIS CA 95650 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 628,694.73 0.00 2. a. Extra Work 135,163.73 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 763,858.46 0.00 5. Mobilization 6. Total Work Completed 763,858.46 7. Deductions 0.00 40,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 763,858.46 40,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 40,000.00