Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 22-321-11-30 06-1F4404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-KER-119-30.1/30.9 NONE Progress payment No. 001 Payment period ending: 08-30-22 GRANITE CONSTRUCTION COMPANY 3005 JAMES RD BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 307,014.34 307,014.34 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 307,014.34 307,014.34 5. Mobilization 6. Total Work Completed 307,014.34 7. Deductions -30,000.00 -30,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 277,014.34 277,014.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 277,014.34