Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 23-304-15-07 06-1F7204 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-TUL-198-14.6/14.6 NONE Progress payment No. 008 Payment period ending: 10-12-23 MCM CONSTRUCTION INC PO BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 642,325.42 143,327.71 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 642,325.42 143,327.71 5. Mobilization 6. Total Work Completed 642,325.42 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 632,325.42 133,327.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 133,327.71