Dept. of Trans. PROGRESS Serial No. Contract No. 26-117-07-14 06-1F9004 PROGRESS PAYMENT VOUCHER %complete: %time: 36% 100% Location: Federal Project: 06-VAR NONE Progress payment No. 004 Payment period ending: 04-20-26 ARCHER CIVIL CONSTRUCTION LLC 1353 SOUTH J ST TULARE CA 93274 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,231,230.59 950,664.52 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 9,932.85 -9,932.85 4. Earned Subject to Retention 1,241,163.44 940,731.67 5. Mobilization 6. Total Work Completed 1,231,230.59 7. Deductions -100,000.00 -100,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions 0.00 1,986.57 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,141,163.44 842,718.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 842,718.24