Dept. of Trans. PROGRESS Serial No. Contract No. 26-009-10-25 06-1G3504 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 37% Location: Federal Project: 06-FRE-99-233.0 NONE Progress payment No. 005 Payment period ending: 12-20-25 GRUEN ENGINEERING INC 12418 GRUEN ST PACOIMA CA 91331 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 514,759.25 173,921.68 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 514,759.25 173,921.68 5. Mobilization 6. Total Work Completed 514,759.25 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 514,759.25 173,921.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 173,921.68