Dept. of Trans. PROGRESS Serial No. Contract No. 24-128-14-30 06-1G6404 PROGRESS PAYMENT VOUCHER %complete: %time: 37% 50% Location: Federal Project: 06-KER-5-8.0/8.4 NONE Progress payment No. 001 Payment period ending: 05-20-24 DRILL TECH DRILLING & SHORING DBA APEX ROCKFALL MITIGATION 2200 WYMORE WAY ANTIOCH CA 94509 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 347,448.54 347,448.54 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 347,448.54 347,448.54 5. Mobilization 6. Total Work Completed 347,448.54 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 347,448.54 347,448.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 347,448.54