Dept. of Trans. PROGRESS Serial No. Contract No. 25-174-13-36 06-1G7104 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 36% Location: Federal Project: 06-FRE-5-49.9/55.7 NONE 06-FRE-33-16.8/22.8 Progress payment No. 002 Payment period ending: 06-20-25 PAVE-TECH INC 3043 HARDING ST CARLSBAD CA 92008 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 482,643.28 480,568.28 2. a. Extra Work 11,250.00 11,250.00 b. Adustment Comp. 155,376.00 155,376.00 3. Materials on Hand 4. Earned Subject to Retention 649,269.28 647,194.28 5. Mobilization 6. Total Work Completed 649,269.28 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 649,269.28 647,194.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 647,194.28