Dept. of Trans. PROGRESS Serial No. Contract No. 26-112-07-18 06-1G7404 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 95% Location: Federal Project: 06-TUL-63-12.1/21.6 NONE 06-TUL-65-19.2/R20.2 Progress payment No. 006 Payment period ending: 04-20-26 ARCHER CIVIL CONSTRUCTION LLC 1353 SOUTH J ST TULARE CA 93274 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,215,675.31 58,696.93 2. a. Extra Work 25,424.25 0.00 b. Adustment Comp. -26,749.58 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,214,349.98 58,696.93 5. Mobilization 6. Total Work Completed 1,214,349.98 7. Deductions -36,749.58 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,177,600.40 58,696.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 58,696.93