Dept. of Trans. PROGRESS Serial No. Contract No. 26-024-15-48 06-1H9604 PROGRESS PAYMENT VOUCHER %complete: %time: 12% 11% Location: Federal Project: 06-VAR NONE Progress payment No. 001 Payment period ending: 01-20-26 GRIFFITH COMPANY 1128 CARRIER PARKWAY AVE BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 602,724.12 602,724.12 2. a. Extra Work 22,745.29 22,745.29 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 625,469.41 625,469.41 5. Mobilization 6. Total Work Completed 625,469.41 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 625,469.41 625,469.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 625,469.41