Dept. of Trans. PROGRESS Serial No. Contract No. 26-055-19-28 06-1H9604 PROGRESS PAYMENT VOUCHER %complete: %time: 14% 11% Location: Federal Project: 06-VAR NONE Progress payment No. 002 Payment period ending: 02-20-26 GRIFFITH COMPANY 1128 CARRIER PARKWAY AVE BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 602,724.12 0.00 2. a. Extra Work 66,197.08 43,451.79 b. Adustment Comp. 58,631.59 58,631.59 3. Materials on Hand 4. Earned Subject to Retention 727,552.79 102,083.38 5. Mobilization 6. Total Work Completed 727,552.79 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 727,552.79 102,083.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 102,083.38