Dept. of Trans. PROGRESS Serial No. Contract No. 01-081-07-03 06-278614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 84% 06-TUL-198-R4.8/R8.8 Federal Project: ACNH-P198(32) Progress payment No. 31 Payment period ending: 03-20-01 R AND L BROSAMER INC P O BOX 238 ALAMO CA 94507 Escrow No. 01182 Total Estimate This Estimate 1. Contract Itms Without Mobil. 30,731,707.67 282,477.22 2.a. Extra Work 2,145,092.57 38,806.56 b. Adjustment Comp. 708,470.65 108,440.16 3. Materials on Hand 365,109.39 -81,209.94 4. Earned Subject to Retention 33,950,380.28 348,514.00 5. Mobilization 3,900,000.00 0.00 6. Total Work Completed 37,485,270.89 7. Deductions -30,688.95 0.00 8. a.Contract Retentions -1,697,519.01 -17,425.70 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 36,122,172.32 331,088.30 10. Reduction Amt to Escrow 11. Payment to Escrow 1,697,510.00 12. Net Pymt. this Estimate 331,088.30