Dept. of Trans. PROGRESS Serial No. Contract No. 08-056-06-15 06-293304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 61% 41% 06-MAD-99-19.6/22.6 Federal Project: NONE Progress payment No. 15 Payment period ending: 02-20-08 F C I CONSTRUCTORS INC 2100 GOODYEAR RD BENICIA CA 94510 Escrow No. 02290 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,027,369.05 757,987.02 2.a. Extra Work 263,452.40 5,892.99 b. Adjustment Comp. 1,113,297.52 0.00 3. Materials on Hand 723,288.68 -14,084.06 4. Earned Subject to Retention 26,127,407.65 749,795.95 5. Mobilization 4,614,000.00 0.00 6. Total Work Completed 30,018,118.97 7. Deductions -40,451.44 -10,451.44 8. a.Contract Retentions -1,306,370.38 -37,489.79 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 29,394,585.83 701,854.72 10. Reduction Amt to Escrow 11. Payment to Escrow 1,306,370.00 12. Net Pymt. this Estimate 701,854.72