Dept. of Trans. PROGRESS Serial No. Contract No. 05-206-06-28 06-303704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 73% 06-FRE-180-54.3/54.8 Federal Project: ACST-P180(50) PH-P180(50) Progress payment No. 04 Payment period ending: 07-20-05 AGEE CONSTRUCTION CORPORATION P O BOX 629 CLOVIS CA 93613 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 703,155.30 112,934.60 2.a. Extra Work 3,794.43 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 706,949.73 112,934.60 5. Mobilization 48,000.00 0.00 6. Total Work Completed 754,949.73 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 754,949.73 112,934.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 112,934.60