Dept. of Trans. PROGRESS Serial No. Contract No. 10-168-11-20 06-307004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 06-TUL-63-5.8/8.0 Federal Project: NONE Progress payment No. 24 Payment period ending: 06-20-10 TEICHERT CONSTRUCTION P O BOX 15002 SACRAMENTO, CA 95864 Escrow No. 02385 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,157,585.05 202,929.54 2.a. Extra Work 516,994.05 12,161.62 b. Adjustment Comp. 15,843.69 0.00 3. Materials on Hand 4. Earned Subject to Retention 8,690,422.79 215,091.16 5. Mobilization 991,000.00 0.00 6. Total Work Completed 9,681,422.79 7. Deductions -27,814.27 0.00 8. a.Contract Retentions -434,521.14 -10,754.56 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,219,087.38 204,336.60 10. Reduction Amt to Escrow 11. Payment to Escrow 369,130.00 12. Net Pymt. this Estimate 204,336.60