Dept. of Trans. SEMI-FINAL Serial No. Contract No. 03-105-11-01 06-319304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-TUL-99-26.1/48.7 Federal Project: ACNH-P099(431) ACBH-P099(431) NH-P099(431) Progress payment No. 15 Payment period ending: 03-27-03 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 960491539 Escrow No. 01945 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,912,210.34 0.00 2.a. Extra Work 129,399.50 322.00 b. Adjustment Comp. 6,683.89 3,703.65 3. Materials on Hand 4. Earned Subject to Retention 2,048,293.73 4,025.65 5. Mobilization 208,000.00 0.00 6. Total Work Completed 2,256,293.73 7. Deductions -20,000.00 -88.70 8. a.Contract Retentions -99,558.65 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 99,558.65 0.00 9. Total pay to Contractor 2,236,293.73 3,936.95 10. Reduction Amt to Escrow -99,550.00 0.00 11. Payment to Escrow 99,550.00 12. Net Pymt. this Estimate 3,936.95